CONSTRUCTION SCHEDULE IS AT THE END OF THE RDM CONTRACT. THIS WILL BE REVISED FROM
TIME TO TIME AS WEATHER IMPACTS THE SCHEDULE. THIS SCHEDULE WILL STOP AT MEMORIAL DAY
TO LABOR DAY
THE POINTE COUNCIL WILL EMAIL EACH RESIDENT BEFORE CONSTRUCTION ON THEIR BUILDING
BEGINS. IF WE DO NOT RECEIVE AN EMAIL CONFIRMATION, WE WILL TRY TO LEAVE A VOICEMAIL
RDM STATES: As each building comes into the repair cycle, all
the owners are responsible to clear and remove fixtures and furniture from
window areas for us to start. If we have one unit remiss in their obligation, it
would be difficult to initiate the repair, so owner timely compliance is
imperative. I discuss and focus on this aspect with Dave on Tuesday.
RDM PROCEDURES
common areas:
- once the landscape is removed by the Association and the new common area
condition is established, we will photograph each building before we begin
repairs. We will assume responsibility for our disturbance in the work areas and
restore w/ grading and seeding upon completion.
- We intend to set up the storage, dumpster and toilet facility to the "island"
portion of the parking lot. We will photograph these areas before we set up.
There are no heavy delivery trucks involved with this work. However, the
dumpster's require a return drop-off after each pull. Should the asphalt's
integrity be damaged by this operation or any other of our work, we will assume
responsibility in the work areas to repair/patching the area damaged.
Interior:
- we will photograph each unit's condition after Owners clears and remove all
materials in the work areas and before we begin "cutting" the caulk around the
window. If the Owners comply with the directives, there should be minimal
opportunity to damage the unit. We need to only to enter unit twice, once to cut
and another to recaulk.
The photographs referenced are an integral part of our work procedure. These
photos establish a base line for existing conditions and extent of either common
area restoration or interior damage repairs.